I'm having my driveway demo'd and repoured as part of a larger house project. During the demo the workers found that my garage is completely floating above the dirt by about 1-2 ft. I have a drain in my driveway that was inconsistent on working in the past and, well, I found out why it's been working fine for the past few years.
Prior to moving in in 2014 the previous owners (only owners to the house ever) had piers installed. They were performed by a reputable company and I now possess the warranty to it. The garage and the rest of the house so no signs of movement for the last 12 years. The foundation is poured and is 10in thick along with the garage floor. The garage is attached to the house and is about 20x20 ft. Three of the sides are supported by foundation walls. Built in 1956 SW Ohio.
Per the concrete contractors my driveway wins the award for the most well built and brutal driveway they have ever seen with a combination of 0.75 and 0.5in rebar and wire mesh. We are assuming the garage floor is similar.
The concrete contractors have only run into this a few times. They suggested a few options such as:
Removing the garage floor, back filling, and re-pouring.
Core drilling all over and basically pouring footers in the gap.
Core drilling fewer spots and pouring/shoving as much as they can under the garage entrance.
They recommended against using a pumper to fill the void as they, or someone they know, tired it and lifted the whole garage.
I think I'm ok with the last option since the garage is essentially fine and the "footers" they would pour would take up a lot of room under the slab. With that option they will not be digging below grade and the "footers" will only be giving a little extra support and filling the void. Looking for other suggestions on how to handle this.