r/Metrology • u/Moostery42 • 10d ago
General CMM programing
/r/Machinists/comments/1xv6ux9/cmm_programing/Thought I would check with this sub as well.
1
u/Keeperofthecube 10d ago
Do you know the software they are using? That plats a big role. Also tolerances make a big difference along with how many specs need to be measured. I can usually create an initial program for a 30 spec inspection, get it in the machine, work out the bugs, make it a bit more efficient in a day or so. But if I had to use older software it would probably take twice as long.
1
u/Moostery42 10d ago
It is older software. PAS CMM and then it gets sent to M-COSMOS
2
u/Keeperofthecube 10d ago
Ive personally never used m cosmos, I've heard it can be a bit of a bear though. Still depends on how many specs they need to program in, is it a rotating head, is it changing tools often for different features types etc. Sometimes I get a part across my desk and at first glance it feels like it will be quick but once you get into the weeds it takes a lot longer to make sure everything is accurate. Another factor that usually slows me down is that I very rarely get to sit down and only do a program without being pulled away many times for other tasks. Everyt time that happens it takes time to remember where I was when I sit back down.
2
u/Familiar-Bluejay3908 10d ago
I used COSMOS about 25 years ago, and it was...ok, but hardly state-of-the-art at the time. I DID like that you could add sound files to your program, though....
1
u/Moostery42 10d ago
Beeep… music to my ears… beep
And I’m loving a consultant saying that a program should be able to be done in a day.
→ More replies (1)
1
u/Otto_Polymath 10d ago
"used around the world" has nothing to do with how long something takes to perform.
If you are new/recent to programming, it will take longer. More experience and you will speed up and get better at it. Anyone else at the company that programs?
Management starts questioning the programming and I pull out the drawing and we talk about how they would go about it.
1
u/Moostery42 10d ago
Yeah, I’m the new middle management. I’ve got to bridge the gap between what an outside consultant sold to upper management and what’s happening
2
u/Familiar-Bluejay3908 10d ago
The conflict between manufacturing and QC is as old as the hills. In 20+ years of CMM programming, I have never once met a shop manage who was happy with the turn-around time for a CMM program to be made and run. I've told shop managers to send me the schedule a week ahead so that I can get a program at least sketched-out, yet they NEVER do this. So, I just wait and make the program when it arrives.
I specifically told the IT person that I did NOT want email or Teams on the CMM CPU for just this reason...
1
u/Moostery42 10d ago
Yeah, I’m transitioning from the eng team to qc manager. I’ll be trying to keep the other managers off my guys. Minor success this week in that, but I’m still getting some training and we have the c-suite swinging by next week…. So we’ve hidden the boxes in the racking 😇. So many process gaps to correct, but I’m trying not to rush things.
→ More replies (1)
1
u/designmyproduct 9d ago
Setup time swings a lot with feature count, datum structure, tolerances, and whether the part needs head rotation or tool changes, so one day is only a rough rule of thumb. Ask the programmer for the feature count and how the time splits between alignment, collision checks, and prove-out versus writing the program itself. Tracking program time on a few comparable parts will also give you real numbers to discuss with your boss. Interruptions and debugging runs on the machine often make up a big part of the total.
1
1
u/DeamonEngineer 10d ago
General rule of thumb we use is it takes roughly the same time to program it as it takes to program the part for the CNCs.
The more complex the part or the tighter tolerances the longer it takes
1
u/CrashUser 10d ago
As others have said, it depends heavily on complexity and number of features. I generally find in PC-DMIS as things get more complex, ie over 30 or 40 dimensioned features assuming it's not just a big bolt circle, I spend at least as long creating features and dimensioning as I do actually programming the physical measurement itself.
4
u/Familiar-Bluejay3908 10d ago
I'd take a stab at this VERY scant amount of information, but alas, my crystal ball is out for calibration this week....
But, FWIW, "it depends". I just had a 200-feature program with ELEVEN datum structures using SEVEN different datums. Took me 2 DAYS....