General Discussion Change Management Workflow

Hi,

We’re introducing change management for the first time using ITSM.

We’re now deciding the workflow before our ITSM vendor configures it

Our scope covers all IT infrastructure changes including network, servers, virtualization, backup, storage, AD/Entra ID & Databases

Each team has its own Line Manager and another requirement is that Cybersecurity Unit must approve every change

Few things we’re trying to understand

Who should approve a change and in what order?
Who should be the CAB members
Which changes should go to CAB

I’d appreciate any suggestions

12 Upvotes

14 comments sorted by

2

u/Commercial_Growth343 Oct 17 '26

I don't think the order of approvals matters. I haven't seen that personally.

Which changes should go to a CAB .. well my approach to that has always been all of them. In ITSM/ITIL I believe there is a level of change that is common, repeatable, well known that can get away with a smaller CAB. Bigger companies I have worked at do this .. the first one is examined in detail because it is the first but once it is done, it needs less approval next time. I have worked at smaller companies for years so we just do a change, it gets approved, and we have a weekly review meeting to discuss changes and if they are planned, happening now, or recently completed.

I feel you should really come up with your own definition of what a change even is, what an emergency change is, what is not a change etc. Everyone on the team should have a good idea if what they are doing should be a Change and follow the process.

As for the CAB, this can depend on the size of your organization. But I would say generally your own manager/supervisor needs to be on it pretty much universally. Your direct boss should know what you are doing and be OK with it. Then after that is would be people who your change can impact, so an infrastructure change maybe needs one or more people from the infrastructure team for a technical approval. If your change is impacting a specific business unit then someone that represents that business unit (like a BA, or systems analyst that supports that business unit) or if you are big enough then the manager for the BA's/SA's.

The bigger the company, then generally speaking the bigger the CAB and need for formal change review meetings (weekly in my experience).

The bigger the company, the more likely you will have a change window worked out with the business, where most changes take place (ex. third Thursday evening of every month). In that case you need all the IT managers involved for planning and approving the actual work so for example the network team doesn't take down the network during an application upgrade or whatever else.

good luck

3

u/TheSmashy Cyber Infra Arch Oct 17 '26

Oh, you sweet summer children.

Do not make Cyber a bottleneck in your change management process. If you have a scheduled, reoccurring, patch management process, yes it should be tracked as a change, but no, cyber should not have to approve a BAU process. And not every change needs to go to CAB, asses by operational impact.

CAB? You need key stakeholder, that's it. Who owns network, who owns compute, etc..

0

u/[deleted] Oct 17 '26

[deleted]

2

u/Final-Pomelo1620 Oct 17 '26

Thank you for detailed response. This is really helpful.

1- Security Manager must approve every change. If we use a Yes/No checklist instead, how do we stop engineers from just clicking "Yes" on everything to skip Security

2- our management still wants approvals on standard changes

3- Management wants the Head of Infrastructure to approve all changes(after the Line Manager and Security Manager). When should the Head of Infrastructure actually be involved so tickets don't get stuck waiting on them?

Engineer → Team Line Manager (5 teams) → Security Manager → Head of Infrastructure

4- Would it make sense to restrict change request creation to authorized implementation engineers, with their own team’s Line Manager providing the first approval?
End users would raise service requests
If a change is needed, an authorized engineer from the responsible IT team would assess it, prepare the implementation and rollback plans, and submit the change for approval.

→ More replies (2)

3

u/Previous-Low4715 Oct 17 '26

This is great advice. Probably the only thing I would add is to try and figure out a risk score based approach to deciding which lane you’re in, otherwise your engineers will always pick the lane that doesn’t require approval so to speak. been there done that.

2

u/0RGASMIK Oct 18 '26

Yes needing to approve everything quickly becomes a bottleneck. Saw this first hand at a business I was consulting for. Couldn’t reinstall a printer driver on a computer without submitting a formal change request form. Fixing a simple printer issue for one machine became a several hour ordeal and it actually made outages longer when they did happen which was the main reason they implemented it in the first place.

Another site needed to factory reset their network stack. Would have been a 15 minute fix. Instead it was going to take a few weeks to get done because they needed a whole redundancy plan in place and yada yada. Meanwhile the location had no internet, worst that would have happened is they had no internet and the equipment needed to be replaced anyways...

It was so frustrating that I told the manager to go to Best Buy and get a high-performance consumer router and return it when they figure out their shit. Gave her my personal number and told her to call me the night before they came back to do the reset so I can walk her through setting everything back to how it was. They were not required by any regulations to have this much BS in the way which is the only reason I was comfortable circumventing it. They even had locations running off of ISP provided routers.