Ok, so I will caveat this by saying I hate RAG statuses and it's something I really struggle with, so looking for advice - I'm NOT a project manager.
However, I was recently asked to attend a board to report on a research project's status. The research project is iterative, and fairly short term in that it's due to mid 2027. I was asked to provide a number for RAG statuses, one for each milestone and then an overall current RAG status and an overall predicted RAG status.
For current I chose green - the project is currently on track, on budget and adhering to deadlines.
However
For predicted, I reported amber - there are significant risks later down the line, both in terms of budget, risk and quality. Whilst these haven't emerged yet, it didn't feel right to report predicted as green because they're so significant, and indeed very likely.
I was pulled up on this by seniors and told it didn't make sense and that I needed further training (which is honestly fair), but to me, my logic makes sense.
Can anyone please explain to me why the current and predicted have to be the same, and how to make that decision going forward please? Links to explainers or guidance welcomed!